Jinbhuvish Power Generations to set up 2x270 MW Coal based thermal project at Dhanmukh

Project Location : Dhanmukh, Yavatamal, Maharashtra
Project Capacity : 540

Jinbhuvish Power Generations to set up 2x270 MW Coal based thermal project at Dhanmukh in Yavatamal district of Maharashtra. The land requirement for the project is estimated as 240 ha. Out of the identified land, 150 ha is stated to be single crop agriculture land. Water will be obtained from Wadad Dam at a distance of about 8 km.

Latest News

Land Acquisition : Acquired total land of 750 acres Water : Water Resource Department of Maharashtra has allocated the water required for the project Coal linkage : obtained the LOA from WCL Environment clearance: TOR approved. MoEF clearance expected shortly. Financial Closure: Completed

Contact Address :
Jinbhuvish Power Generations Pvt Ltd Corp Office: 155, 15 floor, A Wing , Mittal Tower, Nariman Point,
Mumbai- 400021 40824600 40824666 This email address is being protected from spambots. You need JavaScript enabled to view it.

Pioneer Gas Power to set up 400 MW gas based project at Bhagad

Pioneer Gas Power, belonging to the Pioneer Distilleries is planning to set up a 400 MW gas based combined cycle power plant at Bhagad in Mangaon Tehsil in Raigad district of Maharashtra. The company has invited international competitive bids to select the EPC contractor and may be announced in January 2011.

Pioneer Gas Power Ltd Address : 8-2-311/C, Mithila Nagar, Road No.10, Banajara Hills, Hyderabad 500034 Tel: 040-25342895 /2920 email: This email address is being protected from spambots. You need JavaScript enabled to view it. Mr. Rajeev Puri, Executive Vice President

Latest News

The company has awarded the EPC contract to Tata Projects in December 2011

NTPC plans expansion of Dabhol Combined Cycle Power project

NTPC Ltd is planning to expand the Dabhol Combined Cycle Power project in Ratnagiri district of Maharashtra. The project involves setting up of an additional unit of 2100 MW unit. Out of the 1700 acres in the existing site, still 500 acres is left unutilized. 8.5 mmscmd of gas required for the project is to be sourced from KG basin through Dabhol-Panvel pipeline. The project is yet to get statutory clearances. It has commissioned NIO, Goa to conduct a marine impact assessment study.

More Articles

Custom Search

FacebookTwitterGoogle BookmarksLinkedin

Maharashtra

Free Subscription

For latest updates in Indian Thermal Sector, subscribe here:

Delivered by FeedBurner

Copyright © 2013 Ibis Research Information Services Pvt Ltd. All Rights Reserved.
Contact : Ibis Research Information Services Pvt Ltd., 28, Rajaji Street, NGO Colony
Guduvancherry, Chennai -603 202   Mobile : 0-97898-37940 email : ibischennai@gmail.com Privacy Policy